Key takeawaysQuality

A PMO should be designed to fit the organisation and the level of control needed.Innovation

  • PMOs can operate at portfolio, programme and project levels, and may be permanent, temporary, or mixed.Social responsibility
  • There is no one-size-fits-all model, so structure should reflect culture, goals, resources and policies.
  • Effective PMOs provide an independent critical eye through scrutiny, reporting, and challenge on risks, issues and change.SOCIAL RESPONSIBILITY
  • Common reporting standards and dashboards strengthen governance and make progress transparent to senior decision-makers.Some of the charities we have helped over the years:
  • Clear roles, from PMO head to specialists and officers, help avoid overlaps, manage dependencies, and improve delivery discipline.

PMO Structure | Project Management Office Structure

P3O model example

PMO model example

PMO roles and responsibilities

  • Working with business owners, project and team managers, create strategies for effective project planning , monitoring and delivery;
  • Support the project manager when closing projects;
  • Ensure there are no overlaps with other projects which are part of the same programme;
  • Identify dependencies between projects;
  • Provide an ongoing health check of projects by reassuring whether they will continue to meet their objectives;
  • Report progress to the project manager and project board using management dashboards;
  • Informing projects when strategy changes;
  • Be responsible for the continual improvement of the PMO;
  • Manage the PMO staff.

Project specialist

The purpose is to provide hands-on specialist support to the project manager(s).

The role provides consultancy to the project board(s) or project manager(s) in the form of advice and guidance or facilitated workshops. Workshops might include start up advice, risk analysis, scoping, planning and tailoring of methods.

At the start of a project this role works with the project manager to define an appropriate level of project governance and structured project management.Copied!

ResponsibilitiesKey takeaways

  • Provide a centre of expertise and develop consistent standards and procedures, templates and tailoring guidance. These should coverA RACI matrix clarifies who does the work, who signs it off, and who needs input or updates.
  • Project initiation;Use RACI to reduce role confusion, duplicated effort, and slow decisions on cross-functional projects.
  • Risk analysis;Ensure every task has at least one Responsible character and exactly one Accountable character.
  • Issue and change control analysis;Limit Consulted and Informed assignments to avoid information overload and meeting sprawl.
  • Configuration management;Validate the chart with stakeholders, then keep it visible and updated as the project changes.
  • Planning techniques;Adapt the model when needed, such as RASCI or DACI, and align it to lifecycle phases and Agile ceremonies.
  • Methods and tools;
  • Quality assurance;
  • Project organisation structures.
  • Brief project board and project assurance members on their roles and responsibilities;Contents
  • Provide a fast-track project support service;
  • Design and support project reporting;
  • Build and maintain a register of approved training courses;Contents
  • Build and maintain a repository of good project documentation.

Project officer/coordinator/administratorIntroduction

  • 

ReferencesMinimising conflicts and duplications

[1] AXELOS (2013). Portfolio, Programme and Project Offices. Norwich: TSO. p8.Optimising resource allocation.

[2] AXELOS (2013). Portfolio, Programme and Project Offices. Norwich: TSO. pp149-150.P3O® is a registered trademark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved.You can effectively use RACI matrix in the following situations:

Organisational change or restructuring In practice, the RACI matrix helps to clearly assign each task to one or more Responsible persons. This helps to avoid confusion and ensure that everyone knows who is doing what. The matrix also helps in by identifying who needs to be consulted or informed at each stage of the project. Creating a RACI matrix