PRINCE2 stagesSimon Buehring
Key takeawaysPRINCE2 management stages break a project into manageable chunks, with at least two stages required.
PRINCE2 manages risk and investment by controlling delivery through decision points.Stages are decision-driven and should not be confused with technical phases such as design or testing.
- PRINCE2 management stages break a project into manageable chunks, with at least two stages required.The initiation stage produces the PID, including the business case, project plan, and key management strategies.
- Stages are decision-driven and should not be confused with technical phases such as design or testing.Each stage ends with a stop or proceed decision gate where the project board approves the next stage plan and resources.
- The initiation stage produces the PID, including the business case, project plan, and key management strategies.Stage length is shaped by risk, realistic planning
- Each stage ends with a stop or proceed decision gate where the project board approves the next stage plan and resources.
- horizons, project board availability, and organisational or programme timing.

Manage by stages principlePRINCE2 is a principles-based project management
PRINCE2 is a principles-based project management methodologymethodology. There are . There are 7 principles7 principles which form the foundation stones of the method and everything in PRINCE2 is based upon them. which form the foundation stones of the method and everything in PRINCE2 is based upon them.One of the principles is known as the ‘
One of the principles is known as the ‘manage by stagesmanage by stages’ principle. If you are not applying this principle on your project, it means your project is not a PRINCE2 project.’ principle. If you are not applying this principle on your project, it means your project is not a PRINCE2 project.You can learn more about the
You can learn more about the principles of PRINCE2principles of PRINCE2 by taking either a classroom by taking either a classroom PRINCE2 coursePRINCE2 course, or a , or a PRINCE2 course onlinePRINCE2 course online..So, what is the rationale behind this principle? Let us explain.
So, what is the rationale behind this principle? Let us explain.Management stages
Management stagesA PRINCE2 stage is also known as a
A PRINCE2 stage is also known as a management stagemanagement stage. PRINCE2 management stages are a way of breaking down a project into smaller, more manageable chunks. The minimum number of . PRINCE2 management stages are a way of breaking down a project into smaller, more manageable chunks. The minimum number of PRINCE2 stagesPRINCE2 stages on a project is two. on a project is two.Don’t confuse PRINCE2 stages with phases. They are two different things. People often use phases on
Don’t confuse PRINCE2 stages with phases. They are two different things. People often use phases on projectsprojects to delineate different specialist work on a project. For example, analysis, design, build, test, deploy. PRINCE2 stages, as you will below form key decision points about whether to proceed with or stop the project. to delineate different specialist work on a project. For example, analysis, design, build, test, deploy. PRINCE2 stages, as you will below form key decision points about whether to proceed with or stop the project.PRINCE2 stages can coincide with the start or end of a technical phase, and they can also straddle multiple phases. Similarly, one technical phase might contain multiple PRINCE2 stages.
PRINCE2 stages can coincide with the start or end of a technical phase, and they can also straddle multiple phases. Similarly, one technical phase might contain multiple PRINCE2 stages.The key thing to understand is that technical phases are driven by the technical nature of the work, whereas PRINCE2 stages are driven by the needs of the project’s decision-makers, and the level of risk on a project.
The key thing to understand is that technical phases are driven by the technical nature of the work, whereas PRINCE2 stages are driven by the needs of the project’s decision-makers, and the level of risk on a project.Enhance your skills with our expert-led courses
Initiation stageThe first PRINCE2 stage on a project has a special name. It is called the
The first PRINCE2 stage on a project has a special name. It is called the initiation stageinitiation stage. It occurs when starting up a project. As its name implies, it is where the project gets initiated.. It occurs when starting up a project. As its name implies, it is where the project gets initiated.Initiation is where the project manager develops a
Initiation is where the project manager develops a project planproject plan and detailed and detailed business casebusiness case justifying the investment in the project. During initiation the project manager also prepares strategies for justifying the investment in the project. During initiation the project manager also prepares strategies for managing qualitymanaging quality, risk, issues, changes, sustainability, commercial, communication, and benefits. All this documentation is brought together into one collection known as the project initiation documentation (PID)., risk, issues, changes, sustainability, commercial, communication, and benefits. All this documentation is brought together into one collection known as the project initiation documentation (PID).Planning the next stage
Planning the next stageThe
The project managerproject manager also prepares a more detailed plan for the next management stage. This shows all the work for the next PRINCE2 stage, the timescales and costs, the outputs, and required resources. This is known as the next stage plan. also prepares a more detailed plan for the next management stage. This shows all the work for the next PRINCE2 stage, the timescales and costs, the outputs, and required resources. This is known as the next stage plan.The project’s main decision-makers (the project board) then uses the PID and the next stage plan to decide whether to proceed to the next PRINCE2 stage. If the project board decides the project is worth the costs, timescales, and risks, then they can approve the PID and next stage plan and commit the resources necessary to implement the next PRINCE2 stage.
The project’s main decision-makers (the project board) then uses the PID and the next stage plan to decide whether to proceed to the next PRINCE2 stage. If the project board decides the project is worth the costs, timescales, and risks, then they can approve the PID and next stage plan and commit the resources necessary to implement the next PRINCE2 stage.Something similar occurs at the end of every subsequent management stage, except for the final stage. When the final management stage is reached, this is where the project will close, and so there is no need to create another stage plan because there will be no more stages.
Something similar occurs at the end of every subsequent management stage, except for the final stage. When the final management stage is reached, this is where the project will close, and so there is no need to create another stage plan because there will be no more stages.When taking this decision, if the project is not worthwhile, the project board will stop the project. There will be no more work done except to close the project and salvage anything of value from the work done so far.
When taking this decision, if the project is not worthwhile, the project board will stop the project. There will be no more work done except to close the project and salvage anything of value from the work done so far.The diagram above shows the breakdown of a project into multiple PRINCE2 project stages (the red vertical lines). There is one high-level project plan covering the whole project, and more detailed stage plans – one for each stage.

The diagram above shows the breakdown of a project into multiple PRINCE2 project stages (the red vertical lines). There is one high-level project plan covering the whole project, and more detailed stage plans – one for each stage.Decision gate
Decision gateThe end of each PRINCE2 project management stage is thus a decision gate. The project board decides either to approve the next stage and commit resources to implement it, or it decides to close the project and save the organisation the time, money and resources that was originally planned for the project. A PRINCE2 stage thus forms a ‘stop/proceed’ decision.
The end of each PRINCE2 project management stage is thus a decision gate. The project board decides either to approve the next stage and commit resources to implement it, or it decides to close the project and save the organisation the time, money and resources that was originally planned for the project. A PRINCE2 stage thus forms a ‘stop/proceed’ decision.In this way, PRINCE2 project stages are a less risky approach to taking investment decisions than one big decision taken at the start of the project. In
In this way, PRINCE2 project stages are a less risky approach to taking investment decisions than one big decision taken at the start of the project. In PRINCE2PRINCE2, decisions to ‘stop or proceed’ are taken at the end of all , decisions to ‘stop or proceed’ are taken at the end of all PRINCE 2PRINCE 2 stages. stages.Enhance your skills with our expert-led courses
How long are PRINCE2 stages?The length of a
The length of a PRINCE2PRINCE2 stage depends upon many different factors but includes the following. stage depends upon many different factors but includes the following.Level of risk
Level of riskThe greater the level of uncertainty, the shorter the number of PRINCE2 stages. The riskier the project, the more stages are required. That’s because the project board need to take its ‘stop/proceed’ decisions more frequently to mitigate the risk.
The greater the level of uncertainty, the shorter the number of PRINCE2 stages. The riskier the project, the more stages are required. That’s because the project board need to take its ‘stop/proceed’ decisions more frequently to mitigate the risk.Planning horizon
Planning horizonIt is only possible to plan so far into the future in detail before planning becomes a waste of time. This is known as a ‘planning horizon’. Planning for the future beyond what is realistic is only going to mean the plan will fail because it becomes harder to predict what will happen the further in the future you try to do this.
It is only possible to plan so far into the future in detail before planning becomes a waste of time. This is known as a ‘planning horizon’. Planning for the future beyond what is realistic is only going to mean the plan will fail because it becomes harder to predict what will happen the further in the future you try to do this.Since the
Since the project planproject plan is a high-level plan, the stage plan acts as the detailed plan for each PRINCE2 stage. This covers all the work of the stage. It is this plan that the project approves when it commits to fund the next stage. Therefore, the stage plan must only try to plan for what is a reasonable time in the future. This is the duration of the next PRINCE2 stage. is a high-level plan, the stage plan acts as the detailed plan for each PRINCE2 stage. This covers all the work of the stage. It is this plan that the project approves when it commits to fund the next stage. Therefore, the stage plan must only try to plan for what is a reasonable time in the future. This is the duration of the next PRINCE2 stage.Availability of the project board
Availability of the project boardThe members of the project board are senior managers busy with lots of things, other than a single project. Therefore, their availability becomes a limiting factor in when a PRINCE2 stage boundary occurs.
The members of the project board are senior managers busy with lots of things, other than a single project. Therefore, their availability becomes a limiting factor in when a PRINCE2 stage boundary occurs.Organizational or programme needs
Organizational or programme needsSometimes it makes sense to coincide PRINCE2 stages with external events, such as the start or end of the financial year, when planning for the funding of the next years’ projects might take place. Similarly, if a project is part of a programme, it makes sense that PRINCE2 stages coincides with the major decisions of the programme.
Sometimes it makes sense to coincide PRINCE2 stages with external events, such as the start or end of the financial year, when planning for the funding of the next years’ projects might take place. Similarly, if a project is part of a programme, it makes sense that PRINCE2 stages coincides with the major decisions of the programme.PRINCE2 project lifecycle PDF